Government Code section 65587


(a)

Each city, county, or city and county shall bring its housing element, as required by subdivision (c) of Section 65302, into conformity with the requirements of this article on or before October 1, 1981, and the deadlines set by Section 65588. Except as specifically provided in subdivision (b) of Section 65361, the Director of Planning and Research shall not grant an extension of time from these requirements.

(b)

Any action brought by any interested party to review the conformity with the provisions of this article of any housing element or portion thereof or revision thereto shall be brought pursuant to Section 1085 of the Code of Civil Procedure; the court’s review of compliance with the provisions of this article shall extend to whether the housing element or portion thereof or revision thereto substantially complies with the requirements of this article.

(c)

(1)If a court finds that an action of a city, county, or city and county, which is required to be consistent with its general plan, does not comply with its housing element, the city, county, or city and county shall bring its action into compliance within 120 days. However, the court shall retain jurisdiction throughout the period for compliance with its order and to conform to the requirements of Article 14 (commencing with Section 65750).

(2)

If review by the Department of Housing and Community Development is required, as part of a court order pursuant to Article 14 (commencing with Section 65750), and the review is not timely completed to allow a city, county, or city and county to comply with a court order to bring their housing element into compliance within 120 days, the court may grant a reasonable extension of time for the city, county, or city and county to comply.

(d)

(1)If a court finds that a city, county, or city and county failed to complete the rezoning required by subparagraph (A) of paragraph (1) of subdivision (c) of Section 65583, as that deadline may be modified by the extension provided for in subdivision (f) of that section, the court shall issue an order or judgment, after considering the equities of the circumstances presented by all parties, compelling the local government to complete the rezoning within 120 days or the earliest time consistent with public hearing notice requirements in existence at the time the action was filed. The court shall retain jurisdiction to ensure that its order or judgment is carried out. If the court determines that its order or judgment is not carried out, the court shall issue further orders to ensure that the purposes and policies of this article are fulfilled, including ordering, after considering the equities of the circumstances presented by all parties, sanctions on the city, county, or city and county until the rezoning is complete and in effect.

(2)

Any interested person may bring an action to compel compliance with the deadlines and requirements of paragraphs (1), (2), and (3) of subdivision (c) of Section 65583. The action shall be brought pursuant to Section 1085 of the Code of Civil Procedure. In any such action, the city, county, or city and county shall bear the burden of proof.