Welfare and Institutions Code section 14105.5
(a)
For the purposes of this section, “substantial progress” is defined and evidenced as follows:(1)
For structures of three or fewer stories, completion of the foundations and footings; the structural frame; the mechanical, electrical, and plumbing rough-in; the rough flooring; the exterior walls and windows; and the finished roof.(2)
For structures of more than three stories, a contractor’s schedule of work shall be filed with the department by January 1, 1973. Every three months thereafter, until completion, evidence shall be submitted to the department that construction is progressing on that schedule.(b)
For the purposes of this section, construction of a project is deemed commenced on the date the applicant was so notified by the department, if so notified, or on the date the applicant has completed not less than all of the following:(1)
Submission to the appropriate state agency of a written agreement executed between the applicant and a licensed general contractor to construct and complete the facility within a designated time schedule in accordance with final architectural plans and specifications approved by the agency.(2)
Obtaining the initial permits or approval for commencing work on the project that is customarily issued for projects of the scope of applicant by the governmental agency having jurisdiction over the construction.(3)
Completion of construction work on the project to such a degree as to justify and require a progress payment by the applicant to the general contractor under terms of the construction agreement.
Source:
Section 14105.5, https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=WIC§ionNum=14105.5.