Public Utilities Code section 7809


Any proposed railroad track may be permitted to cross any track already constructed, the crossing being made as provided in Chapter 1 of this division. In laying down the track and preparing therefor, not more than one block shall be obstructed at any one time, nor for a longer period than 10 working days.

Source: Section 7809, https://leginfo.­legislature.­ca.­gov/faces/codes_displaySection.­xhtml?lawCode=PUC§ionNum=7809.­ (updated Jan. 1, 1951; accessed Jun. 29, 2026).

Green check means up to date. Up to date

Verified:
Jun. 29, 2026

§ 7809's source at ca​.gov