Public Utilities Code section 2803


“Interconnection” means the facilities necessary to physically connect the energy source of and the point of use by a private energy producer with the existing transmission facilities of a public utility, and shall include any necessary transformation, compression or other facilities necessary to make such interconnection effective.

Source: Section 2803, https://leginfo.­legislature.­ca.­gov/faces/codes_displaySection.­xhtml?lawCode=PUC§ionNum=2803.­ (updated Jan. 1, 1976; accessed Jun. 30, 2025).