A summary describing the overall progress of the project.(b)
The baseline budget for all project phase costs, by segment or contract, beginning with the California High-Speed Rail Program Revised 2012 Business Plan.(c)
The current and projected budget, by segment or contract, for all project phase costs.(d)
Expenditures to date, by segment or contract, for all project phase costs.(e)
A comparison of the current and projected work schedule and the baseline schedule contained in the California High-Speed Rail Program Revised 2012 Business Plan.(f)
A summary of milestones achieved during the prior two-year period and milestones expected to be reached in the coming two-year period.(g)
Any issues identified during the prior two-year period and actions taken to address those issues.(h)
A thorough discussion of risks to the project and steps taken to mitigate those risks.