Public Utilities Code section 1202.1
(a)
The necessity for the project.(b)
The approval of the location and the engineering plans, including provisions for handling traffic during construction and the work to be performed by each party.(c)
The sum to be advanced by the applicant for the work to be done by the respondent. The commission shall render as promptly as possible an interim decision effective within 20 days on the questions, reserving for a later hearing and decision the question of apportionment of costs. The decision shall also order the respondent to proceed upon receipt of the sum to be advanced by the applicant without delay to perform the work to be done by the respondent, integrating the work with that of the applicant or its contractor in such manner that neither will unreasonably obstruct or delay the work of the other, to the end that the people of the state may have the use of the project at the earliest possible date.
Source:
Section 1202.1, https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PUC§ionNum=1202.1.
(accessed Apr. 24, 2025).