Public Utilities Code section 1098
(a)
The original estimated costs as of the time of certification.(b)
The actual costs to date.(c)
The percentage of the work completed to date.(d)
The estimated costs to completion.(e)
The costs associated with changes made by regulatory bodies to the scope or design of the project.