(a)
The overall project financing plan and the overall project development schedule.(b)
Policies, procedures, and performance standards for such matters as the project’s management control systems; public hearings; location studies, preliminary engineering investigations, and environmental impact studies; plans, specifications, and cost estimates; acquisition of rights-of-way and other related real properties; relocation assistance; contract provisions, bidding and awards, change orders, payments and audits, and contractor claims; and material and equipment testing.
Source:
Section 14085, https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=GOV§ionNum=14085.