Civil Code section 901


A builder may, but is not required to, offer greater protection or protection for longer time periods in its express contract with the homeowner than that set forth in Chapter 2 (commencing with Section 896). A builder may not limit the application of Chapter 2 (commencing with Section 896) or lower its protection through the express contract with the homeowner. This type of express contract constitutes an “enhanced protection agreement.”

Source: Section 901, https://leginfo.­legislature.­ca.­gov/faces/codes_displaySection.­xhtml?lawCode=CIV§ionNum=901.­ (updated Jan. 1, 2003; accessed Jun. 30, 2025).

Green check means up to date. Up to date

Verified:
Jun. 30, 2025

§ 901's source at ca​.gov