If a work of improvement is made pursuant to two or more direct contracts, each covering a portion of the work of improvement:

(a)

The owner may record a notice of completion of a direct contract for a portion of the work of improvement. On recordation of the notice of completion, for the purpose of Section 8412 and 8414, a direct contractor is deemed to have completed the contract for which the notice of completion is recorded and a claimant other than a direct contractor is deemed to have ceased providing work.

(b)

If the owner does not record a notice of completion under this section, the period for recording a claim of lien is that provided in Section 8412 and 8414.

Source: Section 8186, https://leginfo.­legislature.­ca.­gov/faces/codes_displaySection.­xhtml?lawCode=CIV§ionNum=8186.­ (updated Jan. 1, 2011; accessed Jun. 30, 2025).