(a)
Notwithstanding subdivision (g) of Section 454.5 and Section 583, no later than May 1 of each year, the commission shall release to the Legislature the costs of all electricity procurement contracts for eligible renewable energy resources, including unbundled renewable energy credits, and all costs for utility-owned generation approved by the commission. The first report shall include all costs commencing January 1, 2003. Subsequent reports shall include only costs for the preceding calendar year.
(1)
For power purchase contracts, the commission shall release costs in an aggregated form categorized according to the year the procurement transaction was approved by the commission, the eligible renewable energy resource
type, including bundled renewable energy credits, the average executed contract price, and average actual recorded costs for each kilowatthour of production. Within each renewable energy resource type, the commission shall provide aggregated costs for different project size thresholds.
(2)
For each utility-owned renewable generation project, the commission shall release the costs forecast by the electrical corporation at the time of initial approval and the actual recorded costs for each kilowatthour of production during the preceding calendar year.
(b)
This section does not require the release of the terms of any individual electricity procurement contracts for eligible renewable energy resources, including unbundled renewable energy credits, approved by the commission. The commission shall aggregate data to the extent required to ensure protection of the confidentiality of
individual contract costs even if this aggregation requires grouping contracts of different energy resource type. The commission shall not be required to release the data in any year when there are fewer than three contracts approved.
(c)
The commission may combine the information required by this section with the report prepared pursuant to Section 913.3.