CA Pub Util Code Section 103395


(a)

Subject to the limitations of this article, the district may utilize the CMGC project delivery method for public transit projects within its jurisdiction.

(b)

The district may enter into a CMGC project delivery method contract pursuant to this article if, after evaluation of the traditional design-bid-build process of construction and of the CMGC project delivery method in a public meeting, the district makes a written finding that use of the CMGC project delivery method on the specific project under consideration will accomplish one or more of the following objectives: reduce project costs, expedite the project’s completion, or provide features not achievable through the design-bid-build method. This finding shall be made prior to the district entering into a CMGC project delivery method contract. In the CMGC project delivery method proposal, the written findings shall be included as part of an application for state funds for a transit project.
Last Updated

Aug. 19, 2023

§ 103395’s source at ca​.gov