Upon completion of the precise plans and specifications, the work or any portion of it may be done in any of the following ways as ordered by the district board:

(a)

By purchasing the material and doing the work by day labor.

(b)

By purchasing the material and letting a contract for the doing of the work.

(c)

By purchasing only a portion or none of the material and letting a contract for furnishing the balance or all of the material and the doing of the work.