(a)

Except as specified in subdivision (b), in a ratesetting or quasi-legislative case, the commission shall resolve the issues raised in the scoping memo within 18 months of the date the proceeding is initiated, unless the commission makes a written determination that the deadline cannot be met, including findings as to the reason, and issues an order extending the deadline.

(b)

Notwithstanding subdivision (a), the commission may specify in a scoping memo a resolution date later than 18 months from the date the proceeding is initiated, if that scoping memo includes specific reasons for the necessity of a later date and the commissioner assigned to the case approves the date.